Fix: moving date of task when moving date of project was not working
This commit is contained in:
parent
27846d1698
commit
6709d3d377
@ -1204,17 +1204,18 @@ class Project extends CommonObject
|
||||
$this->error.=$task->error;
|
||||
}
|
||||
}
|
||||
|
||||
//print "$this->date_start + $tasktoshiftdate->date_start - $old_project_dt_start";exit;
|
||||
|
||||
//Calcultate new task start date with difference between old proj start date and origin task start date
|
||||
if (!empty($tasktoshiftdate->date_start))
|
||||
{
|
||||
$task->date_start = $this->date_start + ($tasktoshiftdate->date_start - $old_project_dt_st);
|
||||
$task->date_start = $this->date_start + ($tasktoshiftdate->date_start - $old_project_dt_start);
|
||||
}
|
||||
|
||||
//Calcultate new task end date with difference between origin proj end date and origin task end date
|
||||
if (!empty($tasktoshiftdate->date_end))
|
||||
{
|
||||
$task->date_end = $this->date_start + ($tasktoshiftdate->date_end - $old_project_dt_st);
|
||||
$task->date_end = $this->date_start + ($tasktoshiftdate->date_end - $old_project_dt_start);
|
||||
}
|
||||
|
||||
if ($to_update)
|
||||
|
||||